RAPID CITY MPO Agenda Item Summary |
|||
|
|||
Meeting Date: 9/10/2013 |
Commission, Board or Committee: N/A |
||
Staff Contact: Kip Harrington, Transportation Planner II |
PW Committee: N/A |
||
Petitioner: N/A |
Metropolitan Planning Organization: 8/15/13 |
||
Location: N/A |
City Council: N/A |
||
Agenda Title: |
|||
13TP044 – Approve Meade County High Meadows Access Corridor Study Request for Proposals |
|||
Summary: |
|||
The Meade County High Meadows Access Corridor Study Request for Proposals will review the safety and the route of the existing High Meadows road, explore connecting the south side of the City of Summerset to High Meadows Road, and determine the feasibility of providing an alternate access for the High Meadows area. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
Federal Highway Administration Planning Funds (81.95%) $122,925 Meade County Local Match (18.05%) $27,075 Total Funds $150,000
Meade County has paid the local match amount for this contract. |
|||
Recommendation: |
|||
Action: Staff recommends approval of the Meade County High Meadows Access Corridor Study Request for Proposals. |
|||
Options: |
|||
N/A |
|||
Attachments & Links: |
|||
|
|||